Project Progress Dashboard

Annual Operations Plan · DMF Indicators · ADB Overall Rating · Last updated: 30 June 2026

OVERALL ADB PROJECT RATING

● On Track

Key Performance Indicators — Q2 2026

Loan & Grant Disbursement

38%

$9.5M / $24.95M

Hospitals in Construction

3

of 5 — all 5 designed; operations targeted Q3 2028

Health Workers Trained

540

of 900 — 60%

EMR/UHI-Ready Hospitals

6

of 11 — 2026 target: 8 district hospitals

Institutional Delivery Rate

64%

Baseline 49% — Target 80%

Safeguard Compliance

100%

0 non-compliance incidents

Annual Operations Plan

AOP 2026 — Mid-Year Status

ADB-style traffic light ratings for key 2026 Annual Operations Plan activities. Rating as at 30 June 2026.

AOP Activity

Output

2026 Target

Achieved (Jun 26)

ADB Rating

Notes

Civil works — begin construction at 5 hospital sites

1.1

5

3

Some Delay

Wet season delays at the Phongsali hospital site

Equipment delivery — all 5 batches

1.2

5 batches

3.75 batches

On Track

Batch 4 final delivery Aug 2026

FDD approvals — all 5 hospital designs

1.3

5

5

Complete

100% achieved ahead of schedule

PHD capacity building sessions

2

36

30

On Track

12 sessions planned for Q3, across 3 PHOs

Health workers trained

2

400

280

Some Delay

Training accelerated in Q3–Q4

EMR/UHI rollout — district hospitals

3

8

6

Some Delay

Connectivity issues at remote Phongsali district hospitals

EMR/UHI equipment installation (provincial hospitals)

3

100%

75%

Some Delay

Completion target moved to Oct 2026

Safeguard compliance (no incidents)

All

0 incidents

0 incidents

On Track

All EMP monitoring reports submitted

Design & Monitoring Framework

DMF Indicators — Outcome & Impact Level

BAHP’s DMF tracks 24 indicators across impact, outcome, and output levels. The table below shows the 10 headline indicators tracked at the ADB level.

DMF Indicator

Level

Baseline (2024)

2029 Target

Current (2026)

Status

Maternal mortality ratio (per 100,000 live births) in 3 provinces

Impact

284

200

238

On Track

Under-5 mortality rate (per 1,000 live births) in project areas

Impact

56

42

49

On Track

% institutional delivery rate in 3 provinces

Outcome

49%

80%

64%

On Track

% fully immunised children under 1 year in project areas

Outcome

62%

90%

71%

Some Delay

% TB case detection rate in 3 provinces

Outcome

64%

85%

78%

On Track

Hospitals meeting national service standards (completed & operational)

Output

0

5

0

On Track

Health workers trained to national competency standards

Output

0

900

540

On Track

Hospitals connected to EMR/UHI system

Output

0

11

6

Some Delay

% women among trained health workers

Output

38%

50%

58%

Exceeded

GRM grievances resolved within 30 days

Output

100%

94%

On Track

Current Challenges

Obstacles & How We’re Addressing Them

Transparent reporting on the challenges that are causing some delays, and the mitigation actions underway.

Challenge 1

Wet Season Construction Delays — Phongsali

Heavy monsoon rains in 2025 caused 6–10 week delays in foundation works at the Phongsali hospital site. Access roads to this remote upland site were impassable for extended periods.

Mitigation:

Revised construction schedules incorporate weather buffers. Pre-positioned materials on site before monsoon onset. Extended working hours (with community consent) post-monsoon to recover schedule. Project completion not at risk.

Challenge 2

Last-Mile Connectivity for EMR/UHI Rollout

Several remote district hospitals in Phongsali lack reliable 3G/4G coverage, preventing full EMR/UHI deployment across all 8 target district hospitals. Satellite connectivity solutions require additional budget and procurement time.

Mitigation:

VSAT (satellite internet) procurement underway — expected installation Q4 2026. Offline-capable EMR modules deployed as interim solution. ADB approved budget reallocation for satellite costs in April 2026.

Challenge 3

Health Worker Retention in Border Provinces

After training, 14% of trained health workers in border provinces transferred to urban centres within 12 months — reducing the impact of Output 2 capacity building investments.

Mitigation:

MOH introducing 2-year mandatory service commitments for BAHP-funded training recipients. PHDs developing retention packages — housing allowances and career pathways for border-area service. Policy advocacy to MOH underway.

Positive Deviation

Gender Target Exceeded — 58% Women Trained

BAHP’s gender parity target of 50% female training participants has been consistently exceeded — currently at 58%. The GAP scholarship programme has proven highly effective in recruiting women from ethnic minority communities into health worker roles.

Action:

Best practices from the scholarship programme being documented for scaling to other ADB health projects in the GMS region. ADB’s gender team conducting a case study visit in Q3 2026.