Output 1.3 — Pillar 1 ($15.77M)

Facility Design Documents & Construction Supervision

Setting the technical blueprint for all 5 hospitals under BAHP, and engaging a dedicated Detailed Design & Construction Supervision (DDCS) firm to ensure quality construction across Champasak, Phongsali, and Savannakhet.

Facility Design Documents

FDD — The Technical Blueprint

A Facility Design Document is the master reference package for each of BAHP’s 5 hospitals — combining architectural drawings, structural specifications, MEP (mechanical, electrical, plumbing) designs, and functional briefs into one approved document set. No civil works contract can be awarded without a completed, approved FDD.

✓ Architectural and structural drawings to Lao building code
✓ Functional brief aligned to MOH service standards
✓ Bill of quantities for contractor bidding
✓ Solar and rainwater harvesting provisions (climate-resilient)
✓ Disability access compliance — ramps, accessible toilets
✓ Equipment room layouts matched to Output 1.2 specifications

5

Hospital FDDs Completed & Approved

Q2 2024

Detailed Design Milestone Achieved

Detailed Design & Construction Supervision

DDCS — Ensuring Quality Construction

The Detailed Design & Construction Supervision (DDCS) Firm is a strategic consulting firm engaged by the PMU to lead detailed engineering design and provide full-time construction supervision across all 5 BAHP hospital sites. Recruitment for the DDCS Consultant began in Q4 2023, with ADB No-Objection and Executing Agency approval obtained in June 2024.

Feature of Interest — DDCS

What the DDCS Firm Does

• Leads detailed engineering design for all 5 hospitals, building on the approved FDDs
• Provides full-time, on-site construction supervision at each hospital site
• Certifies civil works against approved drawings and specifications before payment
• Supports the PMU’s international Hospital Architect and national Civil Engineer
• Reviews contractor method statements, quality control, and safety compliance
• Reports construction progress monthly to the PMU and ADB

Q4 2023

DDCS Consultant Recruitment Initiated

June 2024

ADB No-Objection & EA Approval Obtained

Design Process

From Site Assessment to Approved FDD

Each of BAHP’s 5 hospitals passes through a rigorous seven-stage design process before works begin — ensuring quality, safety, and value for money.

1

Site Assessment

Topography, soil, flood risk

2

Functional Brief

Service scope & room needs

3

Schematic Design

Floor plan concepts

4

MOH Review

Technical & compliance check

5

Detailed Design

Full structural & MEP (DDCS-led)

6

ADB No-Objection

Prior review for major works

7

FDD Issued

Tender documents released

DDCS Supervision by Province

Three Provinces, One Supervision Team

The DDCS Firm provides dedicated on-site construction supervision at each of BAHP’s 5 hospital sites, sequenced with the construction start dates in each province.

Province

Detailed Design

Construction Start

Target Operations

Status

Phongsali

Complete — Q2 2024

Q3 2025

Q3 2028

Under Construction

Champasak

Complete — Q2 2024

Q4 2025

Q3 2028

Under Construction

Savannakhet

Complete — Q2 2024

Q4 2025

Q3 2028

Under Construction

Next Output

Output 2 — Gender-Responsive Migrant Care